اختبار ذاتي: دورة ادارة مشاريع PMP (نقابة المهندسين ) 150سؤال تحاكي الامتحان الدولي

السؤال 1 من 149

الزمن المتبقي: 180 دقيقة

A project manager is working with a customer’s team on a new project. Product requirements definitions are not yet firm/clear, but the customer wants to start activities asap. The organization is expecting product delivery for a specific date due to a regulatory requirement. Consequently, the project manager has decided to use a hybrid approach. Why did the project manager choose a hybrid approach?