During the fifth sprint, a project lead noticed that none of the customer representatives have participated in any of the sprints. The team told the project manager that they had a prototype ready. What should the project lead do next?
A client has asked the project manager for the program status report. The project manager send the report and then realizes that they accidentally included another manager from the client’s organization on the email. Which approach should the project manager do?
To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project. The group uses a three-point estimating technique. The project manager submits the estimated budget to the project sponsor for approval. The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations. What should the project manager do?
A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past three years. Some members of the project team are pessimistic about the project. How should the project manager do in this situation?
A project manager is assigned to a project. There was a lot of conflict regarding the status of the project and compliance with international regulations. During a regular meeting, the sponsor wanted to know how frequently the risks are being reviewed. Which document project manager should check first?
A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition. However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of contract to sign with the vendor responsible for migrating the systems. The project manager is concerned about controlling finances while delivering results. How should the project manager address this situation?
A project in the execution phase is behind schedule and is missing some materials. The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay. The project manager doesn’t agree with the costs submitted by the contractor for the missing materials. What should the project manager do next?
A few virtual team members are located in a region that generally has good internet connectivity. However, they frequently experience connectivity issues joining team calls during the day. What should the project manager do?
A project manager of a high-risk project is concerned about a delay in the schedule that might force the project to move its go-live date. What should the project manager do next?
During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team. What should the project manager do?
A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, and the user interface software that only has basic specification and a requirement for a user experience design approach. What project management approach should the project manager use?
A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done. What should have been done to avoid this problem?
A key project stakeholder does not attend any of the project meetings and is providing false information that the project team is not delivering on time. What should the project manager do to address this situation?
The project manager has observed that two team members have been arguing with each other openly at meetings. To push their ideas through, each team member individually spoke with the sponsor directly and made decisions without informing the project manager or other team members. What two actions should the project manager take?
A project manager has been given a critical, 5-day window and is allocated a maximum of $100000 as a contingency reserve. After 3 days of work, the project manager completed two actions and spent $80000. What should the project manager do next?
A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team’s efforts while carrying out their daily work. How should the project manager handle this issue?
A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is dissatisfied, stating that the deliverables do not meet the quality specifications. What should the project manager do in this situation?
A company is working on a project to develop an integration of their existing systems. There are known issues in production. What should the project manager do?
A project stakeholder complained that they did not receive an important delivery that was stated in the schedule. The team member responsible for this deliverable explained that they sent an email to the stakeholder advising them that the deliverable would not be delivered on time. What should the project manager have done to avoid this situation?
A customer asks the project manager to complete a project 10 days earlier than planned due to marketing constraints. After discussing this request with the project team, the project manager concludes that this can be achieved if a few activities can be overlapped. Which approach should the project manager take?
A project manager noticed that a team member has been struggling with some tasks, which may ultimately impact the completion date. Team morale is low because they will get the expected bonus if they do not finish on time. What should the project manager do?
A new team member is assigned to a team that consistently delivers each iteration. The new team member doesn’t understand many of the processes followed and begins to negatively impact the schedule. What should the project manager do?
A few major road project is starting, and the contractor has contractually committed to submitting regular status reports and participating in integration meetings. Halfway through the project lifecycle, the contractor stops participating in meetings and submitting reports, stating these items consume too much time.
What should the project manager do first?
On your project you handle known risks by performing the Plan Risk Responses process.
Which of the following would you use when you encounter unknown risks?
A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process. What should the project manager do?
A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager doesn’t have enough resources to achieve this goal. In addition, the schedule doesn’t have activities that can be overlappe That should the project manager do?
In a hybrid delivery for a project, during an iteration review, a subject matter expert (SME) informed the team that new legislation will be published in two months that mostly will impact the project. What should the project manager do?
A company is in need to implement a complex project while changing their current business model. The complex project requires multiple agile teams. What three options should the project manager have the testing team adopt as testing mechanisms?
A project lead has noticed that his agile team, accustomed to agile practices, while performing according to expectations, there is boredom with daily team practices among many of the project team members… What should the project lead do in this situation?
In an agile project that is about 45% complete, most team members are siloed and lack an understanding of each other’s work. What would have most likely caused this communication breakdown?
An agile project is running its 5th iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work. What should the project lead do?
A project manager decides to present a product to key stakeholders after two iterations ONLY. The stakeholders’ feedback was that the team seemed to have missed the mark on many features. What should the project manager do to avoid this in the future?
An agile team is working on a two-week sprint to deliver business value. About one week after the sprint starts, the product owner realizes that a regulatory compliance requirement was missed. The product owner reminds the team that this requirement must be completed in the current sprint or the organization will face a penalty. What should the project manager do to mitigate this risk?
A project sponsor plans to fund the development of a software that has 30 features to be used in 10 different countries. The team feels overwhelmed with the amount of work to be done. What should the project manager do?
A project manager is working on an agile project. The organization decided to implement the scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the scrum approach. The most frequent question raised is what artifact will replace the project schedule. What should be the project manager’s response?
A team member has encountered a technical issue, similar to the one faced in a successfully closed project. However, the team member did not know about the previous project and would like to resolve the issue on their own. What should the project manager do?
A project manager has been asked to participate in the procurement process for a software application that allows customers to buy online e-learning courses. The project manager will take over the project once the supplier has been sourced. What should the project manager do before the project starts?
A senior project manager has included a junior project manager as part of the project team. During a coaching session, the junior project manager asks the senior project manager how to be efficient and reduce rework. What should the senior project manager respond?
You are performing the Plan Risk Responses process for your manufacturing project when encounter a critical risk that may have a high impact on the project completion. All the following are valid responses, except?
A project in the execution phase is behind schedule and is missing some materials. The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay. The project manager doesn’t agree with the costs submitted by the contractor for the missing materials.
What should the project manager do next?
A project manager held a meeting and framed the project schedule. A critical stakeholder, who was not consulted at the time of the schedule discussion, complained that the published dates are not agreeable due to a pre-scheduled task for another assignment. What should the project manager do first?
A project team member identified a procurement risk and sent an email to the project sponsor highlighting the risk. The sponsor forwarded the email to the project manager asking for further details. After speaking with the sponsor, the project manager decided to take preventive action. What document should the project manager review with their team?
A project manager is leading an innovation project that is facing a lot of risks due to a high level of uncertainty. What strategy should the project manager use to manage these risks using an agile approach?
A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis. The team member responds that they do not have the knowledge to perform such an analysis. What should the project manager do?
While creating the work breakdown structure (WBS) with the team, the project manager highlights that the customer requested a proof of concept and will only continue the project based on the results of the proof of concept. A key team member insists that since the customer has a history of requesting proof of concepts and continuing with the projects, the team needs to plan for the whole project, not just the proof of concept. What should the project manager do?
In a project that will deliver a new product using new technology, the project team frequently discusses difficulties that may arise and possible strategies to address them. One team member sets up a meeting with the project manager to discuss their list of challenges and presents an extensive list of items that require continuous attention. How should the project manager use this event to maximize the benefits to the stakeholders?
A project manager is working on a multinational project that has more than 100 stakeholders. The project manager is concerned about the appropriate stakeholder participation and involvement level required for successful project delivery.
What should the project manager do?
A project manager is executing a commercial building project. The project manager discovers that the required building permits have not been obtaine Obtaining the permits will delay the project by one month and will cost the project $35,000. The fine associated with continuing to build without the permit is $1,000 per day. What should the project manager do first?
A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important milestone in a week. What should the project manager do next?
A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer’s standards. In order to ensure this, what should the project manager define and document?